An activity has an early start date of the 10th and a late start date of the 19th. The activity has a duration of four days. There are no non workdays. From the information given, what can be concluded about the activity?
おすすめの解答:A 解答を投票する
Explanation/Reference:
Explanation:
Total float or slack is computed by subtracting the early start date from the late start date, or 19 - 10 = 9.
To compute the early finish date given a duration of 4, we would start counting the activity on the morning of the 10th; therefore, the activity would be completed at the end of day 13, not 14 (10, 11, 12, 13). If we started the activity on its late start date on the morning of the 19th, we would finish at the end of day 22, not 25. Insufficient information is provided to determine whether this activity can be completed in 2 days if the resources are doubled.
Explanation:
Total float or slack is computed by subtracting the early start date from the late start date, or 19 - 10 = 9.
To compute the early finish date given a duration of 4, we would start counting the activity on the morning of the 10th; therefore, the activity would be completed at the end of day 13, not 14 (10, 11, 12, 13). If we started the activity on its late start date on the morning of the 19th, we would finish at the end of day 22, not 25. Insufficient information is provided to determine whether this activity can be completed in 2 days if the resources are doubled.