問題 #: 905
トピック #: 1
An activity has an early start date of the 10th and a late start date of the 19th. The activity has a duration of four days. There are no non workdays. From the information given, what can be concluded about the activity?

おすすめの解答:A 解答を投票する

Explanation/Reference:
Explanation:
Total float or slack is computed by subtracting the early start date from the late start date, or 19 - 10 = 9.
To compute the early finish date given a duration of 4, we would start counting the activity on the morning of the 10th; therefore, the activity would be completed at the end of day 13, not 14 (10, 11, 12, 13). If we started the activity on its late start date on the morning of the 19th, we would finish at the end of day 22, not 25. Insufficient information is provided to determine whether this activity can be completed in 2 days if the resources are doubled.

Hibino 2024-06-08 11:33:04

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡