問題 #: 851
トピック #: 3
問題 #: 851
トピック #: 3
A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.
What should the project manager do?
What should the project manager do?
おすすめの解答:A 解答を投票する
When a high-performing team member's performance declines, it is important for the project manager to understand the underlying reasons. Engaging in a direct conversation with the team member can provide insights into potential personal or professional challenges they may be facing, which could be affecting their work. This approach aligns with the PMBOK Guide's emphasis on project managers being actively involved in team management and performance assessment. It also reflects the principles of Professional in Business Analysis, which advocate for understanding the dynamics affecting team performance and addressing them through appropriate communication and problem-solving strategies.
References:
* PMBOK Guide1
* Engaging Your Team to Greater Project Performance2
* How to Start Improving Your Team Performance as a Business Analyst3
References:
* PMBOK Guide1
* Engaging Your Team to Greater Project Performance2
* How to Start Improving Your Team Performance as a Business Analyst3