試験PMP トピック3 問題851 スレッド

PMI PMPのリアル試験問題集
問題 #: 851
トピック #: 3
A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.
What should the project manager do?

おすすめの解答:A 解答を投票する

When a high-performing team member's performance declines, it is important for the project manager to understand the underlying reasons. Engaging in a direct conversation with the team member can provide insights into potential personal or professional challenges they may be facing, which could be affecting their work. This approach aligns with the PMBOK Guide's emphasis on project managers being actively involved in team management and performance assessment. It also reflects the principles of Professional in Business Analysis, which advocate for understanding the dynamics affecting team performance and addressing them through appropriate communication and problem-solving strategies.
References:
* PMBOK Guide1
* Engaging Your Team to Greater Project Performance2
* How to Start Improving Your Team Performance as a Business Analyst3

松嶋** 2024-07-02 09:40:17

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡