問題 #: 16
トピック #: 1
A team has completed the work in their Aeration backlog earlier than expected. There is still three days left of the iteration, what should the team do now?

おすすめの解答:B 解答を投票する

When a team completes their iteration backlog earlier than expected, the recommended approach in Disciplined Agile is to collaborate with the product owner to pull additional work from the product backlog into the iteration backlog. This approach maintains momentum and ensures that the team continues delivering value without waiting for the next iteration. It promotes agility and maximizes productivity by utilizing any remaining time effectively.
* A. Working on non-critical tasksorD. waiting for other groupsare not effective uses of the team's time and do not align with agile principles of continuous value delivery.
* C. Reporting differences in completion timehelps with future planning but does not address the immediate need to continue productive work.
Thus, the correct answer isB. Work with the product owner to pull more work from the product backlog into their iteration backlog.

加藤** 2025-05-14 10:40:18

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡