試験PMP-JPN トピック2 問題616 スレッド

PMI PMP-JPNのリアル試験問題集
問題 #: 616
トピック #: 2
研究開発チームは 2 年間の取り組みを終えようとしています。プロジェクト マネージャーは、プロジェクトの終了活動に重点を置いています。
どのアクティビティを優先的に考慮する必要がありますか?

おすすめの解答:D 解答を投票する

Explanation
According to the PMBOK Guide 7th Edition, one of the principles of project management is to "enable knowledge sharing". This means that the project manager should facilitate the creation, collection, distribution, and use of project knowledge throughout the project life cycle and beyond. The project manager should also ensure that knowledge transfer activities are executed as planned, such as documenting lessons learned, updating organizational process assets, and transferring deliverables to the customer or sponsor. The PMBOK Guide 7th Edition also states that "closing is the process of finalizing all activities across all aspects of the project". The project manager should prioritize the activities that ensure the completion and acceptance of the project deliverables, the satisfaction of the project stakeholders, and the learning and improvement of the project team and the organization. Therefore, the best answer is D. References: PMBOK Guide 7th Edition, pages 11, 12, 55, 56, 57.

Murakoshi 2026-01-02 04:18:30

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡