高リスク プロジェクトのプロジェクト マネージャーは、スケジュールの遅延によってプロジェクトの「稼働日の延期」が余儀なくされる可能性を懸念しています。プロジェクトマネージャーは次に何をすべきでしょうか?
おすすめの解答:C 解答を投票する
When a project experiences a delay that could impact the schedule, the project manager should capture the risk in the risk register. This allows for the documentation of the risk and its potential impact, as well as the planning of appropriate response actions to mitigate the risk. The risk register is a key tool for risk management in projects, as it provides a structured way to track and monitor risks throughout the project lifecycle. By capturing the risk, the project manager can work on preventing the risk from becoming an issue, which aligns with the proactive approach to risk management advocated by PMI.
References: (Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition and Standards. Project Management Institute.)
References: (Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition and Standards. Project Management Institute.)
美弥** 2026-03-09 10:48:50
コメント
他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。
コメントを通報する
コメント中
今すぐ 新規登録 / ログイン (無料です)。