試験PMP-JPN トピック1 問題637 スレッド

PMI PMP-JPNのリアル試験問題集
問題 #: 637
トピック #: 1
主要プロバイダーの問題により、プロジェクトの主要な成果物の1つが遅延しています。プロジェクトマネージャーはどのように対応すべきでしょうか?

おすすめの解答:D 解答を投票する

When a key provider's issue delays a main deliverable, the project manager should first engage directly with the provider to understand the situation, assess impacts, and identify recovery options. Scheduling a meeting with the provider (D) enables fact-finding (root cause, revised dates), negotiation (expedite, partial delivery, additional resources), and alignment on a corrective action plan and monitoring cadence. This is consistent with procurement management and issue management: collaborate first, then escalate if required. Immediately replacing the provider via change request (A) may be costly, slow, and contractually complex, and should be considered after understanding feasibility and recovery options. Meeting "all stakeholders" (B) is broader than necessary as a first step and can waste time before having concrete information. Seeking sponsor guidance to impose penalties (C) may be appropriate later if the provider is noncompliant and contractual remedies are needed, but leading with penalties can damage collaboration and still may not restore schedule. Provider engagement first supports timely recovery and informed escalation.

Mita 2026-05-05 02:09:52

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡