プロジェクトマネージャーは複雑なプロジェクトを率いています。チームは、プロジェクトに対して頻繁かつ段階的かつ制御不能な変更が発生し、困難に直面しています。プロジェクトマネージャーは何をすべきでしょうか?

おすすめの解答:C 解答を投票する

Frequent, incremental, and uncontrolled changes are classic symptoms of scope creep and weak scope control.
The most effective first step is to strengthen scope management so changes are properly defined, evaluated, approved, and incorporated (or rejected) through a formal process. A detailed scope management plan clarifies how requirements will be collected, how the scope statement and WBS will be developed, how scope will be validated, and-most importantly here-how scope will be controlled. With clear control procedures, the project manager can enforce an integrated change control approach: documenting change requests, analyzing impacts (scope/schedule/cost/risk/quality), obtaining the right approvals, and updating baselines and plans accordingly. While risk, quality, and schedule plans are important, they do not directly address uncontrolled changes. Establishing a strong scope management plan aligns stakeholders on what "done" means, reduces ambiguity, protects baselines, and prevents the team from implementing changes informally.

角え** 2026-05-29 01:12:35

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡