アジャイルチームはプロジェクトのリリース計画を準備しています。
チームがこの計画を完了するために必要な情報は何ですか?

おすすめの解答:C 解答を投票する

The correct answer is C - Amount of work that can be accomplished in an iteration. To create a release plan, an agile team uses its historical or estimated velocity-how much work the team can complete in a single iteration. This information helps forecast how many iterations will be needed to complete the prioritized work in the product backlog.
From the PMI Agile Practice Guide:
"Velocity is used to determine how many iterations are required to complete the release backlog. Release planning requires an understanding of how much work can be completed per iteration to forecast delivery timelines." (PMI Agile Practice Guide, Section 5.3 - Iteration Planning and Velocity) Mike Griffiths adds:
"Teams use their average velocity-the amount of work completed per iteration-as the basis for release planning. This supports predictable and empirical planning." (Mike Griffiths, PMI-ACP Exam Prep, Chapter 5 - Adaptive Planning) Incorrect options:
* A focuses too narrowly on a single story, not the full release.
* B focuses on individual capacity, which is contrary to agile's emphasis on team output.
* D is vague; capacity is better measured by iteration.

宇多** 2026-07-22 12:00:30

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡