Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
正解:B
解答を投票する