Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
正解:A、B、C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option.When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify thereasonwhy the project transaction controls are notapplied.
(Choose the best answer.)
(Choose the best answer.)
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
When implementing Project Performance Reporting, your customer has the following requirements:
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)