CPIM 無料問題集「APICS Certified in Production and Inventory Management」

The formula to calculate the Inventory turns is:

Suppose company manufactures paint from a base color and adds tints to arrive at the final color. Suppose there are 10 tints and a final color is made by mixing any three of them with the base. There are 70 possible colors (10*9*8=720). Forecasting and planning production for 720 items is a difficult task. It is much easier if:

正解:B、D 解答を投票する
The operation that controls the work feeding the bottleneck and must operate at a rate equal to the utput of the bottleneck so the time buffer queue is maintained is known as:

Which one of following is not an important factor in supply chain?

The files contained in the database are of two types which are:

shows the quantities needed and when manufacturing intends to make use or use them.

In considering open shop orders, capacity requirement planning account for:

1. Wrong product or specification
2. Wrong amount (too little or too much)
3. Wrong shipping date (too early or too late)
These are common errors in that occur all the time and require constant attention.

Take as an example the supply chain of organizations that represent the flow from raw silicon used to make computer chips to the delivery and disposal of the computer itself:

What is illustrated here is but one chain of a set of different component chains that represent a network of suppliers and distributors for a product to manage a supply chain one must:

The specific way in which materials move depends upon which of the following factor?

Backward scheduling is used to determine when an order must be started.

Frozen zone, slushy zone and liquid zone are the part of

Over a 4-week period a work center produced 540 standard hours of work was available for 640 hours, and actually worked 480 hours. Calculate the utilization and the efficiency of the work center.

The immediate or most current period is called

What is responsible for establishing the flow of materials into the firm, following up with the supplier, and expediting delivery?

What is responsible for executing the master production schedule and the material requirements plan?

The material requirement plan authorizes production activity control (PAC):

Each of the following actions would reduce safety stock levels EXCEPT:

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡