Which of the following is correct about test progress monitoring?
I. According to ISQTB syllabus, Product Risks, Defects, Tests, Coverage and Confidence are 5 dimensions that can be used to monitor test progress.
II. Confidence is measured via surveys and questionnaires and outcome is subjective to the person responding.
Ill. Various metrics are used to measure the product risks, tests and coverage.
IV. One outcome of the progress monitoring could be to relax the test exit criteria.
I. According to ISQTB syllabus, Product Risks, Defects, Tests, Coverage and Confidence are 5 dimensions that can be used to monitor test progress.
II. Confidence is measured via surveys and questionnaires and outcome is subjective to the person responding.
Ill. Various metrics are used to measure the product risks, tests and coverage.
IV. One outcome of the progress monitoring could be to relax the test exit criteria.
おすすめの解答:C 解答を投票する