試験PK0-005J トピック2 問題237 スレッド

CompTIA PK0-005Jのリアル試験問題集
問題 #: 237
トピック #: 2
プロジェクトスポンサーは首相に対し、現在の財務状況の概要を提供するよう求めた。PM が使用するのは、
分析用の燃焼チャートは次のとおりです。

グラフに基づくと、プロジェクトの現在の状況は次のどれですか?

おすすめの解答:A 解答を投票する

The project manager can use the burn up chart to analyze the current status of the project based on its scope
(value delivered), budget (cost), and schedule (time). A burn up chart is a graphical tool that shows how much
work has been completed (burned up) versus how much work remains (scope) over time. It also shows how
much budget has been spent (burned up) versus how much budget remains (budget) over time. A burn up chart
can help to monitor and control the project progress and performance and identify any variances or deviations
from the plan. The chart given shows that both scope and budget lines are above their respective target lines at
any given time point. This means that less work has been completed than planned (scope variance) and more
money has been spent than planned (budget variance) at any given time point. Therefore, the project is behind
schedule and over budget.

Uraga 2024-04-22 11:58:31

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。