試験PK0-005 トピック1 問題21 スレッド

CompTIA PK0-005のリアル試験問題集
問題 #: 21
トピック #: 1
A project was closed according to the planned project schedule. Security teams later identified that one of the
contractors stole data after the project's closure. Which of the following would have most likely prevented the
data from being stolen?

おすすめの解答:A 解答を投票する

Removing access means revoking the contractor's permissions to access the project data, systems, and devices
after the project is closed. This is a crucial security measure to prevent unauthorized access, misuse, or theft of
sensitive data by external parties. Closing contracts, project sign-off, and project evaluation are important steps
in the project closure process, but they do not necessarily prevent data theft by themselves. They may involve
formal agreements, documentation, and feedback, but they do not address the technical aspects of data
security. References = CompTIA Project+ Study Guide: Exam PK0-005, Third Edition, Chapter 14: Closing
the Project, page 3771; 9 Ways to Prevent Third-Party Data Breaches in 20232; 3 Ways to Prevent Data Theft
by Contractors3

Wakabayashi 2024-06-11 11:31:14

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡