問題 #: 315
トピック #: 2
During the execution phase, a new PM was assigned to a project. The PM received a request to add new
functionality to the system that is being developed. While the PM was conducting a preliminary review with
the team, the technical lead highlighted that this functionality request was rejected during the planning phase.
Which of the following documents is the best source for the PM to use to confirm this assertion?

おすすめの解答:D 解答を投票する

A change log is a document that records and tracks the changes that are made to the project scope, schedule,
budget, or quality. It helps the project manager to monitor and control the project performance and ensure that
the changes are aligned with the project objectives and stakeholders' expectations. A change log can also
include information such as the change description, impact, status, approval, and date. A change log is the best
source for the PM to use to confirm the assertion that the functionality request was rejected during the
planning phase, as it would show the details and reasons for the rejection12.

Mori 2026-08-20 09:24:30

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡