A building contractor has a fixed-price contract to construct a large building. It is estimated that the building will take 2 years to complete. Progress billings will be sent to the customer at quarterly intervals. Which of the following describes the preferable point for revenue recognition for this contract if the outcome of the contract can be estimated reliably?

おすすめの解答:B 解答を投票する

Under the percentage-of-completion method, revenues and expenses are recognize based on the stage of completion at the balance sheet date if the outcome of the contract can be estimated reliably. For a fixed-price contract, the outcome can be estimated reliably if total revenue can be measured reliably.2) it is probable that the economic benefits of the contract will flow to the enterprise.3) contract costs to complete and stage of completion can be measured reliably, and4) contract costs can be clearly identified and measured reliably so that actual and estimated costs can be compared.

长*雅 2024-09-28 03:38:06

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡