次のうち、プロジェクトの見積もり、予算、およびコストの変更の管理方法を定義するのはどれですか?
おすすめの解答:A 解答を投票する
Explanation
A cost management plan is a document that defines how the project will be estimated, budgeted, and how changes to cost will be managed. It is a subsidiary plan of the project management plan and it describes the processes, tools, techniques, and methodologies that will be used to plan, execute, monitor, and control the project costs. A cost management plan also specifies the level of accuracy, units of measure, organizational procedures, reporting formats, and thresholds for cost variances and corrective actions. References:
Section 7: Project Cost Management - Q & As for the PMBOK Guide Sixth ..., section 7.1, page 1 Project Cost Estimation: How to Estimate Project Cost - ProjectManager, under What Is a Project Budget?
Project cost management basics - Clockify, under Step #1: Plan the resources
A cost management plan is a document that defines how the project will be estimated, budgeted, and how changes to cost will be managed. It is a subsidiary plan of the project management plan and it describes the processes, tools, techniques, and methodologies that will be used to plan, execute, monitor, and control the project costs. A cost management plan also specifies the level of accuracy, units of measure, organizational procedures, reporting formats, and thresholds for cost variances and corrective actions. References:
Section 7: Project Cost Management - Q & As for the PMBOK Guide Sixth ..., section 7.1, page 1 Project Cost Estimation: How to Estimate Project Cost - ProjectManager, under What Is a Project Budget?
Project cost management basics - Clockify, under Step #1: Plan the resources
Fujisaki 2024-10-07 12:37:49
コメント
他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。
コメントを通報する
コメント中
今すぐ 新規登録 / ログイン (無料です)。