試験CTAL-TM-001 トピック1 問題33 スレッド

ISTQB CTAL-TM-001のリアル試験問題集
問題 #: 33
トピック #: 1
Refer to SCENARIO 3
You are the Test Manager for a software house called "MakeMyApp" that specialise in mobile phone applications, agile techniques are used for all software development projects.
A new project is underway to develop enhancements to a 'photo sharing' application, known as
'PictureFriend'. There are two types of user account available -Premium Users and Guest Users. Guest users only have limited functionality available. The enhanced features to PictureFriend are:
* Feature 1: Guest Users can share photos with other Guest Users and Premium Users;
* Feature 2: Premium Users can edit pictures before posting to their account;
* Feature 3: Premium Users can create '3D-effect' photographs
The requirements for each feature will be broken down into a number of User Stories with acceptance criteria created for each of them. User Stories are planned and delivered in 2-week 'Sprints'. The project will have 3 sprints.
Which of the following are test planning activities that would be MOST appropriate for Sprint 1?
a) Analyse the risk for each of the user stories in sprint 1
b) Publish lest progress reports throughout the sprint
c) Arrange informal reviews of the user stories by the test team
d) Plan an automated system test suite for the user stories.
e) Specify system test conditions at a detailed level for all user stories Chose one of the following options:
SELECT ONE OPTION

おすすめの解答:B 解答を投票する

笹井** 2025-12-04 09:38:28

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡