You just handed over the Defect Accepted and Deferred report to your Maintenance team.
Which testing activity are you performing? [1]
Which testing activity are you performing? [1]
おすすめの解答:D 解答を投票する
The correct answer is D. Test Closure. This is because test closure is the final activity of the test process, in which the test team evaluates the test results, reports the outcomes, identifies the lessons learned, and hands over the testware and the defect reports to the maintenance team. The Defect Accepted and Deferred report is a document that lists the defects that have been accepted by the stakeholders and deferred to be fixed in future releases. By handing over this report to the maintenance team, the test team is performing the test closure activity. Test Closure - ISTQB not-for-profit association Reference: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Test Closure - ISTQB not-for-profit association
石川** 2025-12-04 09:45:32
コメント
他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。
コメントを通報する
コメント中
今すぐ 新規登録 / ログイン (無料です)。