You are planning the testing for an emergency product update required to correct a serious security issue and to improve system maintainability of a key product in your company's catalogue. It has been estimated that the historical cost to the company for the security issue in this system has been $375,000.
In the last year a total of 10 reported "live' incidents were reported, resulting in a total external failure cost of S110.000 to correct.
The cost of prevention for this project has been estimated as $78,500 and from the development you have learned that the average cost of detection was $1,250 and the average cost of internal failure was $7,450 Which one of the following statements about cost of quality is TRUE? SELECT ONE OPTION

おすすめの解答:B 解答を投票する

Yamamoto 2026-06-16 03:00:10

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡