A manufacturer is implementing Dynamics 365 Supply Chain Management to create blends of oil and industrial lubricant.
The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.
You need to define the production life cycle stages.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity.
You need to define the production life cycle stages.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

おすすめの解答:

1 - Create a production order.
2 - Estimate the order.
3 - Schedule production jobs.
4 - Release the order.