プロジェクト チームのマネージャーは、組織に特定のイニシアチブを提供する責任があります。彼らは、マネージャーがこのイニシアチブの現在の状態を発表する月次会議の準備をしています。アジャイル プロジェクト リーダーは、現在のイニシアチブの状態を記載した次のメールをマネージャーに送信します (添付資料 A を参照)。
バックログ全体を完了するには、いくつのスプリントが必要ですか?
おすすめの解答:A 解答を投票する
Step 1: Identify Total Story Points in the Backlog
From the backlog table:

Total story points = 6 + 4 + 8 + 4 + 21 + 7 + 5 + 9 + 3 + 5 = 72
Step 2: Determine the Team's Velocity
The risk register mentions a burn reduction of 1 story point per sprint from sprint 4 to sprint 6 due to a holiday schedule. However, assuming a normal velocity of 5 story points per sprint, we can estimate sprint completion.
Normal sprint velocity: 5 story points per sprint
Reduced velocity for sprints 4-6: 4 story points per sprint
Step 3: Calculate Total Sprints Needed
* First 3 sprints: 5 points per sprint # 5 × 3 = 15 story points completed Sprints 4-6: 4 points per sprint # 4 × 3 = 12 story points completed Remaining story points after sprint 6: 72 - (15 + 12) = 45 story points Remaining sprints needed at normal velocity (5 story points per sprint): 45 ÷ 5 = 9 sprints Total Sprints Required Sprints 1-6: Already planned.
* Additional 9 sprints needed.
Total sprints to complete the backlog: 6 + 9 = 15 sprints.
From the backlog table:

Total story points = 6 + 4 + 8 + 4 + 21 + 7 + 5 + 9 + 3 + 5 = 72
Step 2: Determine the Team's Velocity
The risk register mentions a burn reduction of 1 story point per sprint from sprint 4 to sprint 6 due to a holiday schedule. However, assuming a normal velocity of 5 story points per sprint, we can estimate sprint completion.
Normal sprint velocity: 5 story points per sprint
Reduced velocity for sprints 4-6: 4 story points per sprint
Step 3: Calculate Total Sprints Needed
* First 3 sprints: 5 points per sprint # 5 × 3 = 15 story points completed Sprints 4-6: 4 points per sprint # 4 × 3 = 12 story points completed Remaining story points after sprint 6: 72 - (15 + 12) = 45 story points Remaining sprints needed at normal velocity (5 story points per sprint): 45 ÷ 5 = 9 sprints Total Sprints Required Sprints 1-6: Already planned.
* Additional 9 sprints needed.
Total sprints to complete the backlog: 6 + 9 = 15 sprints.