試験ITIL-4-Specialist-Monitor-Support-Fulfil-JPN トピック1 問題86 スレッド

Peoplecert ITIL-4-Specialist-Monitor-Support-Fulfil-JPNのリアル試験問題集
問題 #: 86
トピック #: 1
サービスマネージャーは、「監視とイベント管理」活動の有効性を確保するために、バリューストリームをマッピングしています。この作業のどの段階で、マネージャーは主要なステークホルダーと最初に連携すべきでしょうか?

おすすめの解答:A 解答を投票する

In ITIL 4, engaging stakeholders early in any process is crucial to ensuring alignment and understanding of expectations. In the context of monitoring and event management, the scoping stage is where the service manager defines the objectives and scope of the value stream mapping exercise. Engaging stakeholders at this point helps clarify their expectations and ensures that their needs are taken into account throughout the exercise.
Scoping Stage: This is the initial phase where the purpose, boundaries, and goals of the exercise are defined. Engaging stakeholders at this stage is critical for setting the right direction.
Option A ("During the scoping stage, to ensure that expectations are understood") is the correct answer because engaging stakeholders at the start ensures that their expectations are aligned with the goals of the exercise.
Incorrect Options:
Option B: Engaging stakeholders during the service value stream walk happens after scoping, making it less effective for setting initial expectations.
Option C: Workflow evaluation is a later stage where impacts are assessed, not the best time for first engagement.
Option D: Reflection and planning come after the value stream has been mapped, making it too late for initial engagement.

中村** 2026-04-28 07:02:26

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡