In SAP Central Business Configuration, which activities can you perform in the Product-Specific Configuration Phase?
Note: There are 3 correct answers to this question.
Note: There are 3 correct answers to this question.
おすすめの解答:B,C,E 解答を投票する
Comprehensive and Detailed in Depth Explanation:
Product-specific configuration in SAP CBC adjusts system settings.
B: Correct. Sales orgs can be added.
C: Correct. Billing blocks are configurable.
E: Correct. Approval thresholds are adjustable.
A, D: Incorrect. Scope and building blocks are fixed earlier.
Product-specific configuration in SAP CBC adjusts system settings.
B: Correct. Sales orgs can be added.
C: Correct. Billing blocks are configurable.
E: Correct. Approval thresholds are adjustable.
A, D: Incorrect. Scope and building blocks are fixed earlier.