During the PI Planning event, when are planning adjustments agreed upon?

おすすめの解答:B 解答を投票する

Explanation
Planning adjustments are agreed upon during the management review and problem-solving meeting in the PI planning event. The management review and problem-solving meeting is a session that occurs at the end of day one of the PI planning event. In this session, the management team reviews the draft plans of all the teams in the ART, identifies any issues or risks that need to be resolved, and proposes any changes or adjustments that are necessary to achieve the program objectives. The management team then communicates their feedback and recommendations to the teams on day two of the PI planning event. References: PI Planning, Management Review and Problem-Solving

鹿野** 2025-03-27 01:49:31

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡