問題 #: 25
トピック #: 7
問題 #: 25
トピック #: 7
During the PI Planning event, when are planning adjustments agreed upon?
おすすめの解答:B 解答を投票する
Explanation
Planning adjustments are agreed upon during the management review and problem-solving meeting in the PI planning event. The management review and problem-solving meeting is a session that occurs at the end of day one of the PI planning event. In this session, the management team reviews the draft plans of all the teams in the ART, identifies any issues or risks that need to be resolved, and proposes any changes or adjustments that are necessary to achieve the program objectives. The management team then communicates their feedback and recommendations to the teams on day two of the PI planning event. References: PI Planning, Management Review and Problem-Solving
Planning adjustments are agreed upon during the management review and problem-solving meeting in the PI planning event. The management review and problem-solving meeting is a session that occurs at the end of day one of the PI planning event. In this session, the management team reviews the draft plans of all the teams in the ART, identifies any issues or risks that need to be resolved, and proposes any changes or adjustments that are necessary to achieve the program objectives. The management team then communicates their feedback and recommendations to the teams on day two of the PI planning event. References: PI Planning, Management Review and Problem-Solving
鹿野** 2025-03-27 01:49:31
コメント
他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。
コメントを通報する
コメント中
今すぐ 新規登録 / ログイン (無料です)。