問題 #: 81
トピック #: 6
問題 #: 81
トピック #: 6
変更要求によって生成された変更タスク-通常の変更タスク
ワークフローには以下を含める必要があります。
ワークフローには以下を含める必要があります。
おすすめの解答:C 解答を投票する
Explanation
Change tasks may be created manually or may be created automatically when Changes enter the Implement phase and the workflow triggers a Change Request - <type> change tasks sub-workflow.
Change tasks that re late to t he specific Change being implemented should be created manually prior to entering the Assess or Authorize States, so the specific Change Tasks involved may be incorporated into the review process.
Automatically-generated tasks may include standard, administrative tasks common to all Changes of a specific type. Automatically generated tasks per Change type include:
Emergency
* Implement
* Post implementation test ing
Normal
* Implement
* Post implementation testing
Standard
* Implement
* Post implementation testing

Change tasks may be created manually or may be created automatically when Changes enter the Implement phase and the workflow triggers a Change Request - <type> change tasks sub-workflow.
Change tasks that re late to t he specific Change being implemented should be created manually prior to entering the Assess or Authorize States, so the specific Change Tasks involved may be incorporated into the review process.
Automatically-generated tasks may include standard, administrative tasks common to all Changes of a specific type. Automatically generated tasks per Change type include:
Emergency
* Implement
* Post implementation test ing
Normal
* Implement
* Post implementation testing
Standard
* Implement
* Post implementation testing