070-177 無料問題集「Microsoft TS: Microsoft Project Server 2010, Configuring」
You have a Project Server 2010 environment. The finance department reports that Task A on Project 123 is out of funding. You need to configure Project Server 2010 so that:
*Resources cannot enter time on Task A in Project 123.
*The task remains active. *These changes take effect immediately.
What should you do?
*Resources cannot enter time on Task A in Project 123.
*The task remains active. *These changes take effect immediately.
What should you do?
正解:B
解答を投票する
You have a Project Server 2010 environment. You have a single OLAP cube that your executives are using for data analysis. The Department lookup table lists Departments A and B.
You need to create a view that shows total project resource costs for Department B, without allowing access to information for Department A.
What should you do?
You need to create a view that shows total project resource costs for Department B, without allowing access to information for Department A.
What should you do?
正解:C
解答を投票する
You have a Project Server 2010 environment. A project manager creates a project plan. When attempting to update the project plan, the project manager cannot open it with read/write permissions. You need to ensure that the project manager can open and update the project plan.
What should you do?
What should you do?
正解:D
解答を投票する