DRAG DROP
You are developing a web application. Currently, the test team tests the website on a Hyper-V virtual machine (VM) named WebTest. The majority of the test cases explicitly reference WebTest.
The test team wants to divide into two independent teams to speed testing, and has indicated that they will likely create a third test teamsoon.
You need to define a strategy that provides separate test environments for each team with as little impact on the tests as possible.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
正解:
Your company network includes Microsoft Visual Studio Team Foundation Server (TFS) 2012 and Microsoft System Center 2012.
You need to monitor your company's application infrastructure.
What should you configure?

解説: (JPNTest メンバーにのみ表示されます)
You are developing a release plan for a new project.
You need to create a risk management plan.
Which three activities or elements should you include in your plan? (Each correct answer presents a complete solution. Choose three.)

正解:B、C、E 解答を投票する
DRAG DROP
Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage the software development process. You are using the Microsoft Visual Studio Scrum process template on your TFS Team Project.
Your product owner adds new product backlog items to your backlog.
You need to estimate how many sprints are necessary to complete the work in your backlog.
You have set a value for the Effort field for each product backlog item found in your backlog as a first step.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:
You are part of a scrum team that needs to identify user stories to complete in the next sprint.
What should the scrum master do?

You manage several developers who are working on multiple applications.
A business analyst requests an audit trail of work item changes for all prospective releases.
You need to implement a strategy to provide the audit trail.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

正解:E、F 解答を投票する
You are developing an application that has several automated builds that build, perform code analysis, and unit test portions of your code. Your team also performs peer review for code changes in an informal manner.
You need to meet the following requirements:
- Provide documentation on quality checks and reviews for any changes to the code
base.
- Ensure code quality.
- Maintain your team's efficiency.
What should you do?

You are a lead developer for your company. You are responsible for a managed application with an existing codebase.
Customers report that the software is unstable. Management wants you to lead an effort to add unit testing to the application.
You need to identify the part of the application that will benefit most from adding unit tests. The goal is to achieve better software quality for the most users.
Which section of code should you target? More than one answer choice may achieve the goal. Select the BEST answer.

Your company's help desk support team comprises a single individual using an Excel spreadsheet to track tickets.
You want to improve the flow of information between the help desk and your development team.
You need to ensure that the lead developer receives updates only when new software defects are reported by the help desk.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

正解:C、D 解答を投票する
You are developing a new application. The application will require rapid changes after it is in production.
You need to implement practices that promote high quality and ensure the code is maintainable.
Which three practices should you implement? (Each correct answer presents part of the solution. Choose three.)

正解:A、C、E 解答を投票する