HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.

Use the drop-down menus to select the answer choice that answers each question.

You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.

Use the drop-down menus to select the answer choice that answers each question.

正解:

DRAG DROP
You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

正解:

Explanation:

References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-
7E775482-AC84-4F4A-BBD0-592F9AC91953
You are a project manager for an organization that uses Microsoft PPM to manage project resources. You are responsible for several projects.
Your organization is trying to improve the resource management maturity level, and has just finished the training on the new process for all project and resource managers.
Resource requests must be submitted based on units less than or equal to 75 percent, leaving 25 percent of the resources' capacity for administrative work.
You need to enter the resource requests.
What should you do?
Your organization is trying to improve the resource management maturity level, and has just finished the training on the new process for all project and resource managers.
Resource requests must be submitted based on units less than or equal to 75 percent, leaving 25 percent of the resources' capacity for administrative work.
You need to enter the resource requests.
What should you do?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
DRAG DROP
You are an administrator for your company's Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
Some users report they spend too much time scrolling left and right in a view named Team
Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
You need to reduce the amount of scrolling.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You are an administrator for your company's Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
Some users report they spend too much time scrolling left and right in a view named Team
Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
You need to reduce the amount of scrolling.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.