70-498 無料問題集「Microsoft Delivering Continuous Value with Visual Studio Application Lifecycle Management」

Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage the software development process. You use the Microsoft Visual Studio Scrum 2013 process template on your TFS Team Project.
You work with the product owner to define and prioritize the Product Backlog.
Due to new business regulations, a group of product backlog items need to be
implemented sooner than initially planned.
You need to raise the business value of the affected product backlog items.
Which two actions should you perform? Each correct answer presents a complete solution.

正解:B、C 解答を投票する
Your company is considering implementing an application lifecycle management (ALM) strategy.
You need to identify the return on investment (ROI) of implementing an ALM strategy.
Which three benefits should you recommend? (Each correct answer presents part of the solution. Choose three.)

正解:A、C、E 解答を投票する
Your development team uses the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template.
You need to determine the process to obtain the most accurate estimates for each user story in your product backlog.
What should you do?

Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM) practices.
You are implementing Scrum as the process framework for new projects. The scrum master will publish daily progress reports to the product owner and key stakeholders.
You need to view daily progress and identify if bottlenecks are occurring in the development process.
Which report should you use?

解説: (JPNTest メンバーにのみ表示されます)
---
You manage a highly complex project by using Microsoft Visual Studio Team Foundation Server (TFS) 2012 for application lifecycle management (ALM).
The project has the following characteristics:
The development team is multi-disciplined, executes all work that is required, and
has a high degree of autonomy.
A key stakeholder acts as product owner to create, prioritize, and manage dynamic
product requirements.
You plan and complete requirements in three week cycles.
- You do not need to keep track of an audit trail.
You need to select a development process.
What are two possible development processes you could select to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

正解:A、E 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A development team is attempting to use Scrum as its process framework. You join the team as the new scrum master.
During a meeting, a developer states that his "task is done."
You need to describe to the team how the word "done" relates to Scrum.
What should you do?

解説: (JPNTest メンバーにのみ表示されます)
----
You develop an n-tier application that includes the following components:
Database
Data access layer
Business logic layer
Presentation layer (website)
The database has approximately 100 tables and stores large amounts of data.
You need to select a unit testing strategy to verify the business logic layer.
What should you do?

You are the product owner for a new application. You have the list of product backlog items (PBIs) with assigned business values for the first release of the application. You will be working with an established scrum master and development team. You know the team's capacity and the planned sprint duration.
You need to plan the release schedule based on your existing backlog.
Which three actions should you and the team perform? (Each correct answer presents part of the solution. Choose three.)

正解:B、E、F 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You manage a project for which the team has not delivered all of the story points committed to in a previous sprint.
You want to define the amount of work the team can commit to for the next sprint of the project.
What should you do?

You create a layered web application. The service layer includes a suite of nUnit tests for the code. The web application contains JavaScript and has no tests.
You configure a build agent running as a service and create an automated build.
You need to include unit testing in the development and automated build of the application. You need to achieve this goal with the least amount of impact to the development team.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

正解:A、C 解答を投票する