74-344 無料問題集「Microsoft Managing Programs and Projects with Project Server 2013」

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?

You are a program manager who uses Project Server 2013 and Project Professional 2013. You have administrative rights.
Your project managers create subprojects for your program-level master project. You insert the subprojects into your master project file by using Project Professional 2013. You are unable to save the master project file.
You need to ensure that your master project file appears with its subprojects when you use the Project Web App (PWA).
What should you do?

You are a team member in an organization that uses Project Server 2013. Each week you report progress on multiple projects that are managed as Microsoft SharePoint task lists.
You need to update task progress on multiple projects from one page.
Which page should you use?

You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?

Your organization is performing a Portfolio Analysis in Project Server 2013.
You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data, which will be part of the project information in Project Server 2013.
You plan to provide different simulations to your organization by using those parameters and returning the best prioritization.
This organization has two different unit directors, who have the final decision on the consolidated Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection.
Which element should you use?

You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved, and the director wants to understand the impact to the overall project schedule prior to formally approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project schedule including duration, work, and cost.
What should you do?

You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has experience with Microsoft SharePoint task lists. The free form tracking method has been selected in Project Server 2013.
You plan to create task assignments.
You need to implement update procedures that meet the following requirements:
Resources need to be able to report on a task when it is completed. Resources should NOT have the ability to report on partially completed tasks. Resources should be able to easily and quickly update project tasks.
Which two update procedures should you implement? (Each correct answer presents part of the solution. Choose two.)

正解:C、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?

You are a project manager who uses Project Online.
You build and publish a resource plan for your project. You check the resource demand in the Resource Availability screen.
You do not see the correct demand as defined in the resource plan.
You need to see the correct demand.
What should you do?

You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?

解説: (JPNTest メンバーにのみ表示されます)