AACE-PSP 無料問題集「AACE International Planning & Scheduling Professional (PSP)」

What is a key first step in developing a critical path method schedule?

Identify the minimum project duration.

What is the relationship depicted between Activity G and Activity H?

Estimate to complete (ETC) is __________________.

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

If Activity E's duration changes to 4 months, what is the overall duration of the project.

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Under which circumstance should one perform resource-leveling calculations?

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡