AD0-E903 無料問題集「Adobe Workfront Project Manager Professional」

A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?

解説: (JPNTest メンバーにのみ表示されます)
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?

解説: (JPNTest メンバーにのみ表示されます)
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?

解説: (JPNTest メンバーにのみ表示されます)
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?

解説: (JPNTest メンバーにのみ表示されます)
What is unique to a Scrum iteration?

解説: (JPNTest メンバーにのみ表示されます)
What are two ways to associate milestone steps to tasks? (Choose two.)

正解:B、C 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

解説: (JPNTest メンバーにのみ表示されます)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡