What criteria does the product owner use to sequence the backlog? Note: There are 2 correct answers to this question.

正解:A、C 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Which of the following cloud services are available on SAP Business Technology Platform? Note: There are 3 correct answers to this question.

正解:A、D、E 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
How do you set up Scrum teams? Note: There are 2 correct answers to this question.

正解:B、C 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
When applying a cloud mindset in a greenfield implementation, which of the following should you consider? Note: There are 2 correct answers to this question.

正解:C、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Which of the following are SAP Activate workstreams? Note: There are 2 correct answers to this question.

正解:A、B 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
What is one of the key activities performed towards the end of the Explore phase?

解説: (JPNTest メンバーにのみ表示されます)
You are transitioning to SAP S/4HANA. In which phase do you adjust custom code?

解説: (JPNTest メンバーにのみ表示されます)
You are implementing SAP S/4HANA Cloud, public edition for your customer. How do you activate the pre-configuration?

解説: (JPNTest メンバーにのみ表示されます)