A user has entered planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a product. For the coming months, requirements with requirement type LSF (derived from the main strategy 10) have been planned. The user would like to change the requirement type from LSF to VSF planning with final assembly (in accordance with planning strategy 40) for requirements in the production plan that have already been saved.
Which of the following statements are applicable in this case? (Choose two.)
Which of the following statements are applicable in this case? (Choose two.)
正解:A、B
解答を投票する
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned order with a similar quantity amount. The customer order and the planned order both have deadlines on work days but not on the same work day; the planned order has a later deadline. The project team member cannot find a rescheduling message referring to this deadline misalignment in the stock/requirements list. What reasons could there be for the missing message? (Choose two.)
正解:C、D
解答を投票する
The master data for a logistical process is to be stored in the SAP ECC system. In this context, you require the production versions for subsequent planning and production. You know a mass maintenance transaction that you could use here. Where else in the SAP ECC system could you define production versions?
正解:C