A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
The project manager has following information about duration for an activity: * Most likely [tM] - 15 days * Pessimistic [tP] - 20 days * Optimistic [tO] - 10 days What is the estimated duration of this activity, according to the triangular distribution technique?
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?