Stakeholder requirements were approved for a business process reengineering initiative along with the creation of a roadmap.
Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) modify in the stakeholder requirements?
Requirement attribute values
Requirement description
Requirement performance measures
正解:
Scope model
Explanation:
Requirement attributes are additional pieces of information that provide more details about each requirement1. They can include information such as priority, source, status, owner, risk, complexity, etc1. When the product roadmap is modified due to changing market conditions, the BA should modify the requirement attribute values to reflect the new situation and communicate the impact to the stakeholders2. For example, the priority of some requirements may change, the status of some requirements may be deferred or cancelled, the risk of some requirements may increase or decrease, etc2. Modifying the requirement attribute values helps the BA to manage the requirements effectively and ensure alignment with the business objectives and stakeholder needs3.
Requirement description is the statement that captures what the requirement is about and what it intends to achieve1. It should be clear, concise, consistent, and testable1. Requirement description does not need to be modified unless the requirement itself changes or is clarified4.
Requirement performance measures are the criteria that are used to evaluate the degree to which the requirement meets the stakeholder expectations and the business value1. They can include metrics such as quality, timeliness, cost, customer satisfaction, etc1. Requirement performance measures do not need to be modified unless the stakeholder expectations or the business value change5.
Scope model is a graphical representation of the boundaries and relationships of the solution and its components1. It can include diagrams such as context diagram, scope diagram, feature model, use case diagram, etc1. Scope model does not need to be modified unless the scope of the solution changes or is refined6. Reference: 1(https://www.iiba.org/business-analysis-certifications/ccba/), 2(https://www.iiba.org/business-analysis-certifications/ccba/ccba/), 3(https://www.techno-pm.com/blogs/project-management-concepts/ccba), 4(https://www.simplilearn.com/project-management/ccba-certification-training), 5(https://www.oreilly.com/library/view/ccba-and-cbap/9781838825263/),
6 (https://www.apm.org.uk/blog/how-to-engage-stakeholders-who-keep-changing-project-requirements/)
Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align with the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?

解説: (JPNTest メンバーにのみ表示されます)
A business analyst (BA) is tasked with designing a method of ensuring that the requirements captured during the elicitation sessions satisfy the needs and expectations of the customer experience, within an initiative. The BA identifies a way that the stakeholder requirements can be structured to ensure realization of the desired customer experience. Which viewpoint describes the approach taken by the BA to structure the requirements?

解説: (JPNTest メンバーにのみ表示されます)
Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?

解説: (JPNTest メンバーにのみ表示されます)
In order to define the business need for an organization, there are two inputs. What are the two inputs a business analyst will need to define the business need?

解説: (JPNTest メンバーにのみ表示されます)
You are the business analyst for your organization and you're working with your stakeholders to assess the organization's readiness for the solution. As part of this assessment, you'll perform a cultural assessment. What is the purpose of this assessment?

解説: (JPNTest メンバーにのみ表示されます)
As a business analyst in your organization, you must understand the difference between operative rules and structural rules. What is the difference between structural rules and operative rules?

解説: (JPNTest メンバーにのみ表示されます)
After a walk-through of the requirements specification with the business users, the group determines that five requirements are now mandatory due to new government regulations. What should the business analyst (BA) do following the meeting?

解説: (JPNTest メンバーにのみ表示されます)
Consider a business analyst who is completing the business analysis tasks of specifying and modeling requirements for an organization. This task can help an organization achieve all of the following objectives except for which one?

解説: (JPNTest メンバーにのみ表示されます)
A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?

解説: (JPNTest メンバーにのみ表示されます)
In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?

解説: (JPNTest メンバーにのみ表示されます)
Which stakeholder(s) will be involved to determine if the requirements can be implemented?

解説: (JPNTest メンバーにのみ表示されます)
Stakeholders need a financial report that can be published and distributed to multiple end users. They would also like the report to be developed within a specific time frame and within cost. What must the business analyst (BA) do to achieve this goal?