CCP 無料問題集「AACE International Certified Cost Professional (CCP)」
You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:
unable to be calculated from the information given
unable to be calculated from the information given
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses What is the amount of capital recovery with salvage?

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses What is the amount of capital recovery with salvage?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
Which of the following statements of the measures of central tendency is correct?
Which of the following statements of the measures of central tendency is correct?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
Student will receive scholarship when the GPA is within top 2%. The mean GPA is 2.8 and standard deviation is 0.5.
How high must the GPA be to qualify for the scholarship?
Student will receive scholarship when the GPA is within top 2%. The mean GPA is 2.8 and standard deviation is 0.5.
How high must the GPA be to qualify for the scholarship?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow's hierarchy of needs?
After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow's hierarchy of needs?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?
Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
What Kind of optimization modeling is used in making investment analysis to evaluate the risks associated with the potential investment?
What Kind of optimization modeling is used in making investment analysis to evaluate the risks associated with the potential investment?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?
Answer the question using a straight line depreciation and a 10% interest rate.
If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
A reason for using a Construction Manager type agreement is:
A reason for using a Construction Manager type agreement is:
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:
The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)