CCP 無料問題集「AACE International Certified Cost Professional (CCP)」

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator
designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
In an exit interview, an employee comments that the reason he is leaving the organization is lack of teamwork and cohesion among his co-workers. Which need of Maslow's hierarchy of needs is unmet?

____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.


The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Given a unit price contract between the owner and contractor, each assumes the following:

____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.


The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
A reason for using a Construction Manager type agreement is:

If a project is said to be on a "fast track program/' the fast track method is:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Why is a +/- notation necessary when developing an estimate?

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡