When designing a protocol for overseeing pre-activity meetings, such as quality kick-offs, that effectively engage all relevant stakeholders (e.g., subcontractors, suppliers, project management teams), what aspects are essential for this protocol to ensure all parties are actively involved and their input is effectively integrated into the project planning?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A CCQM is managing a construction project, and their team has recently experienced issues with a long-time supplier who provides critical building materials. Over the past three months, the supplier has delivered late on multiple occasions and there has been a notable increase in material defects. However, the supplier has historically offered the lowest price and has been awarded additional contracts based on this. Which of the following approaches should the CCQM take to address the issue?
正解:C