If outside air has a temperature of 30°C dry bulb and 20°C wet bulb, what is the dew point temperature?

How can commissioning reduce the life-cycle cost to owners and operators?

Electricity costs SO. 10 per kWh. if an electric water heater has an efficiency of 95*6. what is the equivalent price of natural gas per Gigajoule for a natural gas water heater? The natural gas water heater has an efficiency of 95*t based on lower-heating value.
[Natural gas has an energy content of 36.400 K|/m3 (higher-heating value) and 32-760 K/m3 (lower-heating value).] SELECT THE CORRECT ANSWER

解説: (JPNTest メンバーにのみ表示されます)
A facility has the thermal cooling load profile shown in the table below. The utility rate tariff has an on-peak time-of-use billing period that begins at 10:00 a.m. and ends at 7:00p.m. Calculate the storage capacity required for a load-shifting operating strategy, to make sure that no thermal cooling Is generated by the chiller during the on-peak utility rate period.

[Question from the previous image, which was about storage capacity for load shifting, but the table was missing]

When should commissioning be included in the design and construction of a facility?

The temperature in an unconditioned mechanical room is found to typically be around 23°C warmer than ambient air. If the air intake of an air compressor located in the mechanical room is routed through a nearby wall so that ambient air is fed directly to the air compressor's intake, what impact can be expected on the air compressor's energy requirement?

A refrigerant-to-water heat exchanger can be added to air-conditioning equipment to heat water using the waste heat in the vapor compression refrigerant cycle. Where is this type of heat exchanger located in the refrigerant loop?

The International Performance Measurement and Verification Protocol (IPMVP) has how many categories (method options) to determine the performance of an energy- or water-consuming system?

Which of the following statements best describe Demand Control Ventilation (DVC) in Building Automation Systems?

Using an interest rate of 15%, an energy project has a net-present value (NPV) of $3,500. Which statement is true about the project's internal rate of return (IRR)?