What are some of the actions configurators can do when working correct answers to this question

正解:A、C 解答を投票する
What is taken as an input for the demand sensing process? Note: There are 2 correct answers to this question.

正解:B、C 解答を投票する
Which of the following checks for master data and key figures does the Check Mode algorithm trigger? Note: There are 3 correct answers to this question.

正解:B、D、E 解答を投票する
What is a prerequisite for modelling outsourced manufacturers with production capacity using the Supply Optimizer?

You need to create time periods for the time profile in a planning are
a. What should you be aware of when running the Create Time Periods application job?

A company only purchases a license for the SAP IBP S&OP module and wants to maximize the use of its standard functionality. What processes will they be able to cover? Note: There are 3 correct answers to this question O Get system-solving recommendations on how to react to production bottlenecks

正解:B、C、D 解答を投票する
What are some of the prerequisites for configuring a planning area that results in a successful consistency check? Note: There are 2 correct answers to this question.

正解:A、B 解答を投票する
What is an example of a commonly used time-independent key figure?