After adding a few clients over a number of weeks, the backups have been queuing up and going past the backup window. The administrator has been asked to review and adjust NetWorker configuration to allow enough sessions, so the backups complete on time without going into the queue.
Clone window is not a concern at this time.
They checked the configuration and have determined the following.
Server Parallelism = 80
Number of devices = 9
Backup devices = 6
Clone devices = 3
Target session on each device = 4
Max session on each device = 8
There is a total of 21 clients, each with a client parallelism = 4
After doing the calculations, what needs to be done?
Clone window is not a concern at this time.
They checked the configuration and have determined the following.
Server Parallelism = 80
Number of devices = 9
Backup devices = 6
Clone devices = 3
Target session on each device = 4
Max session on each device = 8
There is a total of 21 clients, each with a client parallelism = 4
After doing the calculations, what needs to be done?