In the Enhanced Knowledge Transfer Phase, what is the correct sequence of steps in the Finalize Project Deliverables?


正解:

Explanation:
Cleanup and Run Backups
Update Checklist
Complete Project Documentation
Generate SCR (Service Change Request)
Provide Documentation
In the Enhanced Knowledge Transfer Phase, the sequence of steps to finalize project deliverables ensures that all necessary tasks are completed in an orderly and efficient manner. Here's a detailed breakdown:
* Cleanup and Run Backups:
* Explanation: This step involves ensuring that the system and data are clean and backed up.
It's crucial to clean up any temporary files or unnecessary data and perform backups to safeguard against data loss.
Based on the Dell EMC RCM Workbook upgrade plan, in what sequence should VxBlock components be upgraded?


正解:

Explanation:
VxBlock Central
Network
Storage
Compute
Virtualization
In the Dell EMC RCM (Release Certification Matrix) Workbook upgrade plan, the sequence of upgrading VxBlock components is designed to ensure system stability and minimize disruptions. Here's the detailed reasoning for the correct sequence:
* VxBlock Central:
* Explanation: VxBlock Central is the management and orchestration layer of the VxBlock system.
Upgrading this first ensures that the management tools are compatible with the new versions of the other components and can properly coordinate and monitor the upgrade process.