A network engineer is implementing MLAG using two N-Series switches, MLAG must be set up with 10 Gb ports and connecting to a single S-Series switch that will run 802.3ad to the MLAG Peers. The commands will be identical on the two N-Series switches. All ports on the N-Series switches are available to use. The VLAN that must be used is 10. The management interface on each N-Series switch has already been assigned an IP address.
Which set of commands should be used to meet the requirement for MLAG?




Which set of commands should be used to meet the requirement for MLAG?




正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A network deployment engineer needs to deploy four Dell Networking N1500 series switches. All switches are to be stacked together using 10Gbe ports on each switch and implement OSPF per the deployment plan.
The customer has been shipped only the four switches with SAS stacking cables. No other equipment has been shipped.
Which two issues occur when the network engineer tries to stack all four switches and implement OSPF?
(Choose two.)
The customer has been shipped only the four switches with SAS stacking cables. No other equipment has been shipped.
Which two issues occur when the network engineer tries to stack all four switches and implement OSPF?
(Choose two.)
正解:C、E
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)

Refer to the exhibit.
The deployment engineer needs to use rapid PVST+ so that some traffic is forwarding on all inter-switch links on these three N-Series Switches. To do so, each switch has been set to the lowest spanning-tree priority value for one of the VLANs.
Given the labeled diagram shown, what Spanning-Tree Priority is Switch B advertising for VLAN 20?
正解:D
解答を投票する
A network engineer needs to install five Dell N-Series switches in a stack for a company that is moving to a new building.
The following items are received:
- 5x Dell N4032 switches
- 5x Power cords
- 5x QSFP+ module card
- 120 CAT6 patch cords
- 1x UPS APC 7000
What needs to be provided to enable the network engineer to complete this task?
The following items are received:
- 5x Dell N4032 switches
- 5x Power cords
- 5x QSFP+ module card
- 120 CAT6 patch cords
- 1x UPS APC 7000
What needs to be provided to enable the network engineer to complete this task?
正解:A
解答を投票する