You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration? There are 3 correct answers to this question. Response:
You want to use the Custom Code Migration Worklist via Remote Code analysis using the ABAP Test Cockpit (ATC). How can you get the latest content of the simplification database? Please choose the correct answer.
Which are valid options to check the progress of the database migration in a Microsoft Windows environment? There is correct answers to this question. Response:
You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system? Please choose the correct answer. Response: