HPE2-W09 無料問題集「HP Aruba Data Center Network Specialist」

Refer to the exhibits. Is this how the switch handles the traffic?


Solution: A frame with destination MAC address, 00:50:56:15:16:28, arrives with a VLAN 10 tag on 1/1/1 on Switch-1. Switch-1 encapsulates the frame with VXLAN and an IP header destined to
192.168.1.2.

解説: (JPNTest メンバーにのみ表示されます)
Is this a guideline for establishing a Virtual Switching Extension (VSX) Inter-Switch Link (ISL) between two ArubaOS-CX switches?
Solution: Use the same speed on every link In the ISL.

解説: (JPNTest メンバーにのみ表示されます)
Does this correctly describe the ArubaOS-CX architecture?
Solution: The Aruba0S-CX Network Analytics Engine (NAE) helps admins to manage multiple Aruba0S-CX switches together using familiar CLI commands.

解説: (JPNTest メンバーにのみ表示されます)
Is this how you should position switches in the ArubaOS-CX portfolio for data center networks?
Solution: Deploy Aruba 83xx switches as core switches for very large three-tier data center networks.

解説: (JPNTest メンバーにのみ表示されます)
You are using NetEdit to manage AruDaOS-CX switches. You want to deploy a standard config to the switches, but need the config to include a few device-specific settings such as hostname and IP address.
Is this what you should do?
Solution: Create a conformance validation test to deploy the standard part of the configuration.

解説: (JPNTest メンバーにのみ表示されます)
Does this correctly describe routing information advertised by a VXLAN Tunnel Endpoint (VTEP) that uses EVPN?
Solution: IMET routes advertise the MAC addresses that the VTEP has learned locally in a VXLAN.

解説: (JPNTest メンバーにのみ表示されます)
Is this correct positioning of AtubaOS-CX switches in the data center?
Solution: A data center will use a leaf-spine topology and requires 64 leaf switches. Aruba CX
8325 switches can be a good choice for both the leaf and spine switches.

解説: (JPNTest メンバーにのみ表示されます)
Is this a rule for configuring schedule profiles on an ArubaOS-CX switch?
Solution: With the exception of a single strict priority queue, all queues must use the same scheduling algorithm.

解説: (JPNTest メンバーにのみ表示されます)
Switch-1 and Switch-2 are AruDaOS-CX switches, which are part of a Virtual Switching Extension (VSX) fabric. Switch-2 is the primary member. Switch-2 experiences a power failure while Switch-
1 remains up. Switch-2's power recovers, and Switch-2 reboots.
Is this one of the things that happens when Switch-2 finishes booting?
Solution: Switch-2 wails a period called the link-up delay before it enables Switched Virtual Interfaces (SVls) on its VSX LAGs.

解説: (JPNTest メンバーにのみ表示されます)
Is this a use case for deploying Ethernet Ring Protection Switching (ERPS)?
Solution: connecting multiple data centers at Layer 2 while minimizing the number of dark fiber connections required

解説: (JPNTest メンバーにのみ表示されます)