An organization had three large centralized divisions: one that received customer orders for service work; one that scheduled the service work at customer locations; and one that answered customer calls about service problems. These three divisions were restructured into seven regional groups, each of which performed all three functions. One advantage of this restructuring would be:
正解:D
解答を投票する
According to the Standards, the internal audit activity must evaluate risk exposures relating to which of the following when examining an organization's risk management process?
1) Organizational governance.
2) Organizational operations.
3) Organizational information systems.
4) Organizational structure.
1) Organizational governance.
2) Organizational operations.
3) Organizational information systems.
4) Organizational structure.
正解:A
解答を投票する
An organization is developing a new online collaboration tool for employees. The tool includes a homepage that is customized to each employee according to his department and job function Which of the following engagements should be conducted to ensure that the organization has included all departments and job functions in the system before it is implemented?
正解:A
解答を投票する
Which of the following statements about slack time and milestones are true?
1) Slack time represents the amount of time a task may be delayed without delaying the entire project.
2) A milestone is a moment in time that marks the completion of the project's major deliverables.
3) Slack time allows the project manager to move resources from one task to another to ensure that the project is finished on time.
4) A milestone requires resource allocation and needs time to be completed.
1) Slack time represents the amount of time a task may be delayed without delaying the entire project.
2) A milestone is a moment in time that marks the completion of the project's major deliverables.
3) Slack time allows the project manager to move resources from one task to another to ensure that the project is finished on time.
4) A milestone requires resource allocation and needs time to be completed.
正解:A
解答を投票する
Which of the following statements is in accordance with COBIT?
1) Pervasive controls are general while detailed controls are specific.
2) Application controls are a subset of pervasive controls.
3) Implementation of software is a type of pervasive control.
4) Disaster recovery planning is a type of detailed control.
1) Pervasive controls are general while detailed controls are specific.
2) Application controls are a subset of pervasive controls.
3) Implementation of software is a type of pervasive control.
4) Disaster recovery planning is a type of detailed control.
正解:A