PK0-004 無料問題集「CompTIA Project+ Certification」

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?

A company wants to remodel two areas in a building it is leasing. The company will utilize its own contractors to remodel the areas. The building owners agree to the remodel. Which of the following documents would the owners MOST likely utilize with the business?

Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members.
Which of the following steps should the PM take to make the meetings more productive? (Select two.)

正解:A、D 解答を投票する
Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?

A milestone task on the critical path has been completed.
Which of the following should the project manager notify?

A project team decides to obtain a support contact on one of the hardware infrastructures being used on the project. This is to ensure the project is grounded if an issue with the hardware occurs during the course of the project.
This type of risk response is known as:

解説: (JPNTest メンバーにのみ表示されます)
A new project manager would benefit from additional assistance with documenting project activities.
Which of the following job positions should the project manager request be added to the team?

A project manager is analyzing the cost variances produced when comparing two different projects completions.

Which of the following factors could be causing the increased variance for the four-month projects? (Select two.)

正解:B、E 解答を投票する
A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?

A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?

Which of the following characteristics would stakeholders MOST likely have?

Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)

正解:B、D 解答を投票する