PK0-005 無料問題集「CompTIA Project+ Certification」

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

解説: (JPNTest メンバーにのみ表示されます)
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

解説: (JPNTest メンバーにのみ表示されます)
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





Select the new critical path.
Option A

Option B

Option C

正解:
See the solution below in explanation
Explanation:
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

解説: (JPNTest メンバーにのみ表示されます)
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

解説: (JPNTest メンバーにのみ表示されます)
A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

解説: (JPNTest メンバーにのみ表示されます)
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

解説: (JPNTest メンバーにのみ表示されます)
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

解説: (JPNTest メンバーにのみ表示されます)
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

解説: (JPNTest メンバーにのみ表示されます)
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

解説: (JPNTest メンバーにのみ表示されます)
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

解説: (JPNTest メンバーにのみ表示されます)
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following is the best example of a breach of physical security?

解説: (JPNTest メンバーにのみ表示されます)
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

解説: (JPNTest メンバーにのみ表示されます)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡