PK0-005 無料問題集「CompTIA Project+ Certification」

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

解説: (JPNTest メンバーにのみ表示されます)
During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late.
As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?

解説: (JPNTest メンバーにのみ表示されます)
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

解説: (JPNTest メンバーにのみ表示されます)
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

解説: (JPNTest メンバーにのみ表示されます)
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

解説: (JPNTest メンバーにのみ表示されます)
A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

正解:C、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

解説: (JPNTest メンバーにのみ表示されます)
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

解説: (JPNTest メンバーにのみ表示されます)
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

解説: (JPNTest メンバーにのみ表示されます)
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

解説: (JPNTest メンバーにのみ表示されます)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡