PMI-PBA 無料問題集「PMI Professional in Business Analysis (PMI-PBA)」
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?
Which of the following is the best strategy to define the appropriate acceptance criteria?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.
What should the business analyst have documented?
What should the business analyst have documented?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project that was going well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.
This could have been avoided if:
This could have been avoided if:
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer does not believe that the product meets the requirements.
This occurred because the customer's acceptance test plan:
This occurred because the customer's acceptance test plan:
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A business analyst has been assigned to a project to implement a new phone system for a customer call center.
The business analyst will need to create a business case.
Which of the following components will the business analyst use as input to the business case?
The business analyst will need to create a business case.
Which of the following components will the business analyst use as input to the business case?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)